AASHTO Innovative Highway Technologies Alkali-Silica Reactivity

Transition Plan for AASHTO
May 2000

APPENDIX H
COST AND BENEFIT SURVEY QUESTIONAIRE

The ASR Lead Team is in the process of assessing costs / benefits of Implementation of SHRP the ASR Technologies and improvements developed in cooperation with the Lead States since conclusion of the SHRP projects. The following survey was designed to provide needed information from AASHTO members in order to make this assessment. Your cooperation in filling out this survey, or asking the appropriate personnel in your department to fill it out, would be greatly appreciated. It is understood that some of the information being requested may not be readily available or easily discernible from existing databases. In these cases your best estimate would be appreciated. Please make sure to mark these areas as "est."

The scope of this project goes beyond, and is planned to be more detailed than, the initial FHWA-sponsored study "Summary of SHRP Research and Economic Benefits of Concrete and Structures" outlined in Research Report Number 96-2 and available through the "RoadSavers" program. The data generated through this survey will be made available to all respondents.

The survey has been subdivided in two sections : 1 ) New Construction, and 2 ) Rehabilitation / Repair / Maintenance of existing ASR affected Pavements and Structures.

I. Respondent Information

Your Name  _____________________________________
Your Title   ______________________________________

State ______   Agency ____________________________
Department  _____________________________________

Address _________________________
_________________________
_________________________
Phone
E-Mail
__________________
__________________

Do You Have Internet Access ? _ YES _ NO

Have you attended an ASR SHRP Showcase ? _ YES _ NO

I am responsible for ( Check all Appropriate Boxes ) :
_ New Pavement Construction _ Materials
_ New Bridge / Structure Construction _ Specifications
_ Pavement Maintenance _ Engineering
_ Bridge Maintenance _ Contracting
_ Research _ Purchasing

II. General

Total Lane-Miles of Highways in the State ____________________
Total Lane-Miles of Highways in Concrete ____________________

Total Number of Bridges in the State _________________

Has your state experienced concrete durability problems ? _ YES _ NO

What Percent of all structures ? _____ %

What has been identified as causes for these problems ?
_ Alkali-Silica Reactivity (ASR) _ Alkali-Carbonate Reaction (ACR)
_ D-Cracking _ Freeze-Thaw
_ Sulfate Attack _ Delayed Ettringite Formation (DEF)
_ Construction Problems _ Drying Shrinkage
_ Subbase _ Other

Have there been any "loss of service" incidents due to ASR?

_ YES _ NO _ DO NOT KNOW
If yes, please provide details : _______________________________________
_________________________________________________________________
_________________________________________________________________

If yes, what was the cost to the state? $ ________

II. New Construction

A. Pavement

How Many Lane Miles of Highway are built annually in the State ? _______
What Percent is Concrete Construction ? _________
How many Cubic Yards of Concrete are poured per year ? ________
What is the Typical Cement Content ? ______________
What is Average Material Cost for Concrete ? ______/ cu.yd.

Installed Cost ? ______ / _____

B. Bridges

How many bridges are built annually in the state ? _______
How many cubic yards of concrete are poured / year ? ________
What is the Typical Cement Content ? __________
What is Average Material Cost for Concrete ? ______/ cu.yd.

Installed Cost ? ______ / _____

C. Life-Cycle Costing

For costing purposes, do you use Life-Cycle Costing ? _ YES _ NO
If yes, what is design life for concrete pavement ? _______ years

Bridges ? _______ years

Are user costs evaluated ? _ YES _ NO

Are Construction Decisions made based on LCCA ? _ YES _ NO

D. ASR Mitigation

Do you currently test aggregate for susceptibility to ASR ? _ YES _ NO
If yes, what test procedure do you use ? _______________________________

Do you have Material Specs that address ASR ? _ YES _ NO

(If yes please attach copy).

What Mitigation Technique Does Your State Use (Check all applicable) ?
What additional cost does this add to concrete per cubic yard ?
_ Low alkali cement    Alkali Level _____ Cost : $ _____ / cu.yd.
_ IP Cement - Type : _____________ Cost : $ _____ / cu.yd.
_ Nonreactive Aggregate Cost : $ _____ / cu.yd.
_ Fly Ash Type : _ F _ C
Quantity : _____________ % substitution ?
_ YES _ NO
_ Silica Fume Quantity : _____ % Cost : $ _____ / cu.yd.
_ GGBFS Quantity : _____ % Cost : $ _____ / cu.yd.
_ Other Pozzolan - Specify : _______________ Cost : $ _____ / cu.yd.
_ Lithium admixture Cost : $ _____ / cu.yd.
_ Other - Specify : ___________________ Cost : $ _____ / cu.yd.

If you use mitigation, have current methods been effective ? _ YES _ NO
If NO please provide details : ______________________________________
________________________________________________________________
________________________________________________________________

If you have experienced ASR, and do not now use any mitigation, please indicate what add-on cost per cubic yard of concrete your state would recognize as cost effective to prevent on-set of ASR.

In pavement :
_ $ 0 _ $ 2 _ $ 5 _ $ 8 _ $ 10 _ $ 12 _ $ 15 _ $ 20

In bridges :
_ $ 0 _ $ 2 _ $ 5 _ $ 8 _ $ 10 _ $ 12 _ $ 15 _ $ 20

III. ASR Remediation / Repair and Maintenance

A. General

What is the state's annual expenditure for :

Maintenance / Repair of Pavement - $ ________
What portion is for ASR affected pavement ? _____ %
Maintenance / Repair of Bridges - $ _________
What portion is for ASR affected bridges ? _____ %

What method / procedures does your state use to determine remediation / repair strategies for pavement ? _________________________________
______________________________________________________________
For bridges ? __________________________________________________
_______________________________________________________________

Are user costs evaluated to determine strategies ? _ YES _ NO

What methods are used to determine if a pavement or bridge is affected by ASR ?
_________________________________________________________
_______________________________________________________________

B. ASR Affected Pavement

Does your state have specific strategies for ASR Affected Pavement ?

_ YES _ NO _ DO NOT KNOW

Please rank the following side-effects of ASR in pavement in terms of relative importance in determining repair / maintenance strategies. (1-most important, 8-least important)
____ Joint failure
____ Spalling / potholing / rutting
____ Loss of Ride / Noise
____ Decrease in structural strength / Modulus of Elasticity
____ Buckling / curling
____ Increased freeze - thaw damage
____ Decrease of Service Life
____ Aesthetic concerns

How long does it take for ASR cracking to occur ? _____ yrs

What percentage of the design service life is expected to be lost due to ASR ?
_ 10 % _ 15 % _ 20 % _ 30 % _ 40 % _ 50 % _ 75 %

What Repair / Maintenance Techniques are used with ASR Affected Pavement (Choose all that apply)?
_ Application of sealer - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Hotmix Overlay - Thickness? _____ in.
  Duration? _____ yrs Cost / lane mile? $ _________
_ Thin Whitetopping Overlay - Thickness? _____ in.
  Duration? _____ yrs Cost / lane mile? $ _________
_ Joint Repair - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Patching - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Lithium Treatment - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Crack repair with Methacrylate - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Crack Repair with Epoxy - What type? __________________
  Duration? _____ yrs Cost / lane mile? $ _________
_ Replacement - Type _ Concrete _ Hotmix - Thickness? _____ in.
  Duration? _____ yrs Cost / lane mile? $ _________
_ Other - Please Detail ___________________________________
  _______________________________________________________
  Duration? _____ yrs Cost / lane mile? $ _________

Of the above strategies, which one has been the most effective?
_____________________________________________________
Which the least? _____________________________________

B. ASR Affected Bridges / Structures

Does your state have specific strategies for ASR Affected Bridges / Structures?

_ YES _ NO _ DO NOT KNOW

Please rank the following side-effects of ASR in bridges / structures in terms of relative importance in determining repair / maintenance strategies. (1- most important, 8-least important)
____ Deck failure
____ Spalling / potholing / rutting
____ Loss of Ride / Noise
____ Decrease in structural strength / Modulus of Elasticity
____ Increased Corrosion
____ Increased freeze - thaw damage
____ Decrease of Service Life
____ Aesthetic concerns

How long does it take for ASR cracking to occur ? _____ yrs

What percentage of the design service life is expected to be lost due to ASR ?
_ 10 % _ 15 % _ 20 % _ 30 % _ 40 % _ 50 % _ 75 %

What Repair / Maintenance Techniques are used with ASR Affected Pavement (Choose all that apply)?
_ Application of sealer - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Hotmix Overlay - Thickness? _____ in.
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Thin Whitetopping Overlay - Thickness? _____ in.
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Deck Replacement - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Patching - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Lithium Treatment - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Crack repair with Methacrylate - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Crack Repair with Epoxy - What type? __________________
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Replacement - Thickness? _____ in.
  Duration? _____ yrs Cost / sq.ft.? $ _________
_ Other - Please Detail ___________________________________
  _______________________________________________________
  Duration? _____ yrs Cost / sq.ft.? $ _________

Of the above strategies, which one has been the most effective?
_____________________________________________________
Which the least? _____________________________________

IV. Other Costs to State related to ASR

Please provide approximate annual costs to the state for the following due to ASR. If unknown please leave blank :
1. Testing, Internal : $ _______
2. Testing, Contract : $ _______
3. Inspection : $ ________
4. Engineering Surveys / Studies : $ ________
5. Consultants : $ ________
6. Corrosion : $ ________
7. Line Striping : $ ________
8. Vehicular Damage : $ ________
9. Change to noncorrosive deicers : $ ________
10. User Lawsuits : $ ________
11. User Costs : $ ________
12. Other : $ ________ Please Specify : __________________________

Back to Table of Contents Appendix I

See also the web site for the AASHTO Technology Implementation Group